Morley Drive Drainage Improvement Works
Location: Dianella, WA
Project Start: 1 March 2018
Project Finish: 11 June 2018
Project Value: $ 500k
Client: Main Roads WA
Overview
Tracc Civil’s contract for the Morley Drive Drainage Improvement works includes installing Drainage Unit Systems and supporting infrastructure in the median of Morley Drive near Constance Street and Dianella Drive.
MRWA Pre-qualification R2 was required.
Scope Stage SP1and SP2
-
Earthworks
-
Clearing of selected trees
-
Removal of existing drainage pipes and manholes
-
Stormwater drainage
-
Sheet piling
-
High line boxes
-
Traffic management signage and controls
Project Challenges
-
Very limited working space
-
Very heavy traffic
-
Night/weekend works were required
-
Houses in close proximity to worksite
Managing These Challenges
-
Effective Traffic Management
-
Effective liaising with various stakeholders
-
Vibration monitoring during sheet piling